Commercial Inspections
- Temporary Electrical Service
- Coordinate with CL&P
- Footings
- When forms for footing are in place prior to concrete pour
- Foundation
- If foundation walls are reinforced
- Anchor Bolts
- Only if not visible after framing
- Footing Drains and Foundation Waterproofing
- Prior to any backfill being placed
- Sub-Slab Plumbing, Radiant Heat and Electrical
- Under test and properly bedded
- Rough Framing
- May be done with mech. elec. and plumb. rough-in
- Exterior Wall and Roof Sheathing
- Prior to installation of building wrap for nail pattern inspection)
- Exterior Insulation and Finish System (EIFS)
- Periodic
- Masonry Walls
- Periodic
- Rough Electrical
- May be done with rough plumbing and framing
- Rough Plumbing / Mechanical
- Under test)
- Gas Piping
- Propane or natural gas under test
- Sprinkler
- Chimney / Masonry / Fireplace
- Smoke chamber
- Gas Appliances
- Includes vented and unvented heaters, log sets, ranges, fireplaces, etc.
- Insulation
- Prior to the installation of any wall sheathing
- Zero Clearance Fireplaces and Metal Chimneys
- Before enclosure
- Public Sewer Connection
- Piping and cleanout as-built is required
- Municipal Water Service
- Including meter pits if required
- Electrical Conduits
- Bedded in trench
- Permanent Electrical Service and Meter
- Coordinate with CL&P
- PV Power Systems
- Prior to release to CL&P
- Geothermal Systems
- To be determined based on type of system
- Septic System amd Private Drinking Water Wells
- By Ledge Light Health District sanitarian
- View the Ledge Light Health District website
- Underground Tanks
- Installations
- Sewer Injectors and Grinder Pumps
- Coordinate with utility department
- Secondary Water Meters
- Well or city water
- Retaining Walls
- Over 36 feet
- Final / CO
- When the construction is considered to be substantially complete
- Prior to use or occupancy