Commercial Inspections

  • Temporary Electrical Service
    • Coordinate with CL&P
  • Footings
    • When forms for footing are in place prior to concrete pour
  • Foundation
    • If foundation walls are reinforced
  • Anchor Bolts
    • Only if not visible after framing
  • Footing Drains and Foundation Waterproofing
    • Prior to any backfill being placed
  • Sub-Slab Plumbing, Radiant Heat and Electrical
    • Under test and properly bedded
  • Rough Framing
    • May be done with mech. elec. and plumb. rough-in
  • Exterior Wall and Roof Sheathing
    • Prior to installation of building wrap for nail pattern inspection)
  • Exterior Insulation and Finish System (EIFS)
    • Periodic
  • Masonry Walls
    • Periodic
  • Rough Electrical
    • May be done with rough plumbing and framing
  • Rough Plumbing / Mechanical
    • Under test)
  • Gas Piping
    • Propane or natural gas under test
  • Sprinkler
  • Chimney / Masonry / Fireplace
    • Smoke chamber
  • Gas Appliances
    • Includes vented and unvented heaters, log sets, ranges, fireplaces, etc.
  • Insulation
    • Prior to the installation of any wall sheathing
  • Zero Clearance Fireplaces and Metal Chimneys
    • Before enclosure
  • Public Sewer Connection
    • Piping and cleanout as-built is required
  • Municipal Water Service
    • Including meter pits if required
  • Electrical Conduits
    • Bedded in trench
  • Permanent Electrical Service and Meter
    • Coordinate with CL&P
  • PV Power Systems
    • Prior to release to CL&P
  • Geothermal Systems
    • To be determined based on type of system
  • Septic System amd Private Drinking Water Wells
  • Underground Tanks
    • Installations
  • Sewer Injectors and Grinder Pumps
    • Coordinate with utility department
  • Secondary Water Meters
    • Well or city water
  • Retaining Walls
    • Over 36 feet
  • Final / CO
    • When the construction is considered to be substantially complete
    • Prior to use or occupancy